THE Metropolitan Manila Development Authority (MMDA) has proposed the construction of rainwater impounding facilities inside Camp Aguinaldo to ease recurring flooding on EDSA, with the proposed design released on Wednesday, Aug. 27.
The plan requires detention ponds that will temporarily store excess rainwater during downpours and gradually release it into the EDSA drainage system, leading to the Makiling Creek.

MMDA proposes rainwater facilities in Camp Aguinaldo to mitigate EDSA flooding
As proposed, the project will be implemented in three phases, covering 182 hectares and involving a golf course near Gate 2, another near Gates 3 and 4, and an open space near Gate 6.
For the first phase near Gate 2, the detention pond has a 361-meter perimeter, a 4,650-square-meter area, an 8-meter depth, and a 37,200-cubic-meter capacity, designed for a 25-year return period (15.6 mm per hour over 24 hours), exceeding the needed 36,945 cubic meters.
MMDA’s schematic shows that under normal weather, the water bypasses the pond and flows through the lagoon to EDSA.
During heavy rain, floodgates divert water flow into the pond; after rain, pumps discharge stored water slowly into EDSA toward the Makiling Creek., This news data comes from:http://052298.com
The scope of works covers the impounding area, operations and powerhouse, drainage and electromechanical works, and landscaping and golf course restoration, with a treatment facility under consideration.
MMDA proposes rainwater facilities in Camp Aguinaldo to mitigate EDSA flooding
Officials said operations and maintenance arrangements, and a memorandum of agreement, are still under discussion.
- Japan govt seeks to triple spending on drones
- President Marcos commits to boosting PH digital infrastructure
- Dizon to abolish DPWH internal special investigation team created to look into the flood control anomalies
- Pope meets with Chagos refugees and delivers message about rights of the weak against the powerful
- Immigration: 1st lookout bulletin in effect on 35 individuals, including Discayas, linked to anomalous flood control projects
- PH, Australia, Canada hold joint sea drills
- 'Large shark' kills man off Sydney beach
- LPA off Leyte has low chance of becoming cyclone within 24 hours —Pagasa
- DOJ indicts Abra Mining for fraudulent trading
- No winner in lotto draws for Aug 30